DfT and TfL have jointly announced that Crossrail services will be extended from Maidenhead to Reading. Crossrail announcementTfL Press ReleaseTrains will only run half hourly from Reading with 4 tph from Maidenhead into London.
|
|
|
Post by snowman on Oct 18, 2014 9:45:22 GMT
Not sure if this is the best thread, but a friend has told me following
TBM Ellie will finish second drive (Limmo-Custom House) in next couple of days.
The two TBMs that have been waiting months near Whitechapel are now on the move again, one is being moved through the already excavated platform tunnels and recommences boring end Oct (towards Farringdon), the other will be moved about 3 weeks later, and should recommence mid Nov. Both should reach Farringdon before Easter (which will complete running tunnels). All other TBMs are now finished and removed. Many cross passages are excavated and the tunnelling contracts are now coming to an end. Many sections are moving onto the fit-out contracts
|
|